Both crews began painting unit doors today, as so far, and all is going smoothly. Unit doors will be painted over the next couple of days and is scheduled to finish on Thursday. The doors will be propped open for most of the day to allow the doors to dry.
Below is a schedule of what doors will be painted to day and on Tuesday.
February 28th
Floor 4 – 400, 401, 402, 403, 404, 405, 406, 407, 408, 409, 410, 411
Floor 2 – 201, 202, 203, 208, 209, 210, 211, 212, 213, 214, 222, 223
March 1st
Floor 4 – 412, 413, 414, 415, 416, 417, 418, 419, 420, 421, 422, 423
Floor 2 – 215, 216, 217, 218, 220, 221
They are friendly guys, so please say hi as we work in your suites.
Daryl - Project Manager