Tuesday, March 1, 2011

Schedule update for painting of unit doors


Here is a quick update for the next two days and what doors will be done on those days.


March 2nd

Floor 3 – 300, 301, 302, 303, 308, 309, 310, 311, 312, 313, 314, 323
Floor 1 – 109, 110, 111, 113, 114, 115

March  3rd

Floor 3 – 315, 316, 317, 318, 319, 320, 321, 322

Monday, February 28, 2011

Painting begins on unit doors

Both crews began painting unit doors today, as so far, and all is going smoothly. Unit doors will be painted over the next couple of days and is scheduled to finish on Thursday. The doors will be propped open for most of the day to allow the doors to dry.

Below is a schedule of what doors will be painted to day and on Tuesday.


February 28th

Floor 4 – 400, 401, 402, 403, 404, 405, 406, 407, 408, 409, 410, 411
Floor 2 – 201, 202, 203, 208, 209, 210, 211, 212, 213, 214, 222, 223


March 1st

Floor 4 – 412, 413, 414, 415, 416, 417, 418, 419, 420, 421, 422, 423
Floor 2 – 215, 216, 217, 218, 220, 221


They are friendly guys, so please say hi as we work in your suites.

Daryl - Project Manager

Monday, February 21, 2011

Work progress as of February 21

On the 2nd floor the guys have done a great job with the trim colour around the doors, putting on two coats Friday.  They started painting the walls today and should finish the whole floor by the end of the day. Tomorrow they will paint the trim colour on the 1st floor.

Up on the 3rd and 4th floor the guys are prepping the door frames and walls and should start painting tomorrow morning.

They are doing a great job of cleaning up at the end of the day, leaving almost no traces that they were there.

Daryl - Project Manager

Friday, February 18, 2011

Painting Begins

Congratulations on making a selection on your colour scheme!!

As of today you will begin to see your hallways changing colour. Our crew on floors 1 and 2 will begin painting the accent colour around the unit doors in the hallways with ICI Opal.

Our crew on 3rd and 4th floors are working in the stairwells and continuing with wall prep in the hallways. Expect to see them begin painting the trim colour around unit doors on Monday.

Please take care around your unit doors as they may be wet. Wet paint signs will be posted.

Have a great weekend!


Daryl - Project Manager

Thursday, February 17, 2011

Work update February 17th

The work is progressing well and we are ready to begin painting the 1st and 2nd floors tomorrow morning.  The ceilings are painted on all four floors and they are currently working on painting the ceilings in the stairwells.

As we begin to paint the hallways over the coming weeks please be mindful of the walls as the paint may be drying. We will have signs posted to warn of wet paint.

Thank you for bearing with us through this process.


Daryl - Project Manager

Tuesday, February 15, 2011

Progress update as of February 15th

Work is progressing nicely. The ceiling has been painted with 2 coats on the first and second floors.  The hallway walls on all floors are being mudded and sanded today.  There will be dust in the hallways due to the sanding, but we will be ensuring that your halls are clean at the end of the day. Please bear with us during this process.

We are looking forward to receiving the paint choices you have made so we can start painting the trim and walls on Friday.

We will be requiring access to unit doors starting on February 28th. A schedule has been produced that has been passed to the strata council. Once the schedule has been approved, we will post it here, as well as physically posting it in your lobby.


Daryl - Project Manager

Monday, February 14, 2011

Work progress as of February 14th

Happy Valentine's Day!

Today we are working on sanding the walls and painting the ceilings. Our crews will be working on all floors over the next couple of days prepping walls and painting ceilings. Once the paint scheme has been voted on we will begin painting the hallways and the doors.


Daryl - Project Manager